The US$4.5 billion CGK campus is scheduled to begin service in late 2026, with two more buildings to follow in 2027.
Editor APAC, The Tech Capital
3 Mins
{{formattedDate}}
Digital Edge has reached two milestones at its 500 MW CGK campus in Bekasi, Greater Jakarta, with the structural topping out of its first building and a new power agreement state-owned utility company PLN.
Editor APAC, The Tech Capital
Singapore-headquartered data centre operator Digital Edge has closed its first US$575 million holdi...
Digital Edge and B.Grimm Power have signed a US$880 million green loan to fund the development of t...
Digital Edge, a Singapore-based data centre operator backed by Stonepeak Partners, is weighing stra...
Digital Edge has secured a US$665 million green loan to support the first phase of its 500MW CGK Ca...
Singapore-headquartered data centre operator Digital Edge plans to invest US$4.5 billion to develop...